This past November NYSEG informed the club that the electrical service entering the clubhouse was suspended from a pole that was rotten and as risk of falling. Accompanying the faulty pole was an electrical configuration in the clubhouse, which was in need of an update.

In the frigid month of January the grounds crew installed elctrical conduit to move this service below ground. We'd like to thank Chis Hildreth and Hildreth Electric for re-routing and updating the electric service.

In March the grounds department finished off the job by removing the old pole and installing a new fence to increase storage. The old pole was extremely rotten and definitely was an accident waiting to happen. The pole was so rotten we were able to break it off and pull it down with a rope.